Filter

Support
Wall Lights

MO, PO, VO, CG, & CN - Install Notes

Tabs

Read Article

The recessed fixtures include a Schedule 40 conduit. This conduit can be cut to length but must always fully capture the fixture base. It cannot be cut any shorter than 7–1/2". Follow the step-by-step instructions below to install these lights.

Model Sleeve P/N SCH 40 Size Pipe OD Recommended Core Drill Size
PO 250018590000 1-1/2" 1.9" 2"
VO C2165 N/A 1.78" (custom) 2"
MO 25002060000 2" 2.36" 2-1/2"
CG 250013670000 2" 2.375" 2-1/2"
CN N/A 2-1/2" 2.875" 3"

Step 1

Use the provided conduit and trim length if necessary.

Step 2

Install conduit sleeve into wall during construction. Run fixture wiring through sleeve. *Coupling for VO fixture only.

Step 3

Use voltmeter to ensure 11 to 15 V at fixture.

Step 4

Connect wiring with waterproof connector.

Step 5

Press faceplate into sleeve. Level and orient fixture as desired.

Step 6

* For the concrete ground-mount option, use construction housing. The VO-ST is rated for a load of 992 lbs.

Rate this Article: 
0
No votes yet

Was this article helpful? Yes | No